Archives
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- July 2015
- June 2015
- May 2015
- April 2015
- March 2015
- February 2015
- January 2015
- December 2014
- November 2014
- October 2014
- September 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- December 2013
- November 2013
- October 2013
- September 2013
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- January 2012
- December 2011
- November 2011
- October 2011
- September 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
- March 2011
- February 2011
- January 2011
- December 2010
- November 2010
- October 2010
- September 2010
- August 2010
- July 2010
- June 2010
- May 2010
- April 2010
- March 2010
- February 2010
- January 2010
- December 2009
- November 2009
- October 2009
- September 2009
- August 2009
- July 2009
- June 2009
- May 2009
- April 2009
- March 2009
- February 2009
- January 2009
- December 2008
- November 2008
- October 2008
- September 2008
- August 2008
- July 2008
- June 2008
- May 2008
- April 2008
- March 2008
- February 2008
- January 2008
- December 2007
- November 2007
- October 2007
- September 2007
- August 2007
- July 2007
- June 2007
- May 2007
- April 2007
- March 2007
- February 2007
- January 2007
- December 2006
- November 2006
- October 2006
- September 2006
- August 2006
- July 2006
- June 2006
- May 2006
- April 2006
- March 2006
- February 2006
- January 2006
- December 2005
- November 2005
- October 2005
- September 2005
- August 2005
- July 2005
- June 2005
- May 2005
- April 2005
- March 2005
- February 2005
- January 2005
Meta
Monthly Archives: July 2011
More Mulching Madly
Early start to this Sunday. Bills paid and two month’s filing done before 9:00 am. I’ve just moved servers on the web hosting service in New Jersey that has my web logs, web pages, parts of the family emails, and several domain names. It went fairly smoothly except for the email and I spent the morning trying to sort that out with technical support in New Jersey (or maybe India) and Bridget in Wellington. By mid afternoon I think it is sorted out.
Karola decided to clear branches and blackberry in a band along the top of the ha-ha so that she could give her ewes a wider strip than usual along there. She also pruned the lower branches of the ? Privet which is probably poisonous to sheep. I mulched up most of the brambles and branches along with several other small piles around the garden.
I noticed #403 limping badly so coaxed her with maize to get close enough to grab her. The first three attempts she threw me off but on the fourth attempt we landed up in the mud and I held on. I checked her feet and trimmed them but there didn’t seem to be too much wrong – some infection which I sprayed with antibiotics. As Karola said, the limping may be mostly due to mild mastitis as she nears lambing.
The Cottage Refurbishment
Nothing to report today except that I finally got round to smashing up the broken lavatory bowl from the cottage and we put it in a maize sack in the rubbish which goes out tonight. So Paul and Matthew won’t have to see it sitting on the ground outside the cottage any more.
Weather:-2°C—12°C; 0.1 mm rain [83.9] 06:30
Posted in General
Comments Off on More Mulching Madly
Mulch Noisy Mulch
We did some mulching of branches today – feijoa trimmings and the English Beech branch that fell down some months ago. Karola put up another electric fence across the orchard to let the lambs have some fresh grass before they leave the orchard in August. I put up a similar fence down the top edge of the ha-ha and let the ewes in for some fresh pasture.
The Cottage Refurbishment
Nothing to report today.
Weather:1°C—16°C; 0.5 mm rain [83.4] 06:30
Posted in General
Comments Off on Mulch Noisy Mulch
Ashley is Ashleigh – Of Course
SwimGym then, apart from putting in a couple of short posts to protect karola’s new water metre up at the big shed, I stayed indoors. Karola went to Hastings in the morning for food for the weekend.
Bridget, who dropped in at Burleigh on her way home last night, tells me it’s Ashleigh, not Ashley – Tessa’s baby that is.
The Cottage Refurbishment
I called Kings Fourth Generation Woodworking Ltd in Masterton and got an estimate for roughly how much a kitchen bench of solid Matai would cost – $8000 more or less. Not a whole lot more than stainless steel so very much to be preferred.
Still no sign of the estimates from The English Craftsman so I called. Finally, they emailed us this evening. Six existing windows refurbished, 4 new big sash windows, 9 casement windows, floors cleaned and waxed – $60,000. Rather too expensive.
Weather:8°C—17°C; 0.1 mm rain [83.6] 06:00
Posted in General
Comments Off on Ashley is Ashleigh – Of Course
Bridget Leaves For Wellington.
Cold sunny day. Lunch with our Bridget and granddaughters at Pernel’s Fruit World then they and Karola went off to Napier and played mini-golf on the waterfront.
They returned mid afternoon and Bridget and Natalie and Alex said their goodbyes and set off home at 4:30 pm, going first to Bulls to see the new niece, Tessa’s baby Ashley.
The Cottage Refurbishment
Bridget Geenty, kitchen designer, came round as planned mid morning and we, with our Bridget, discussed the cottage kitchen design until lunchtime. BG had some good suggestions and I think Karola would like her to work on the cottage kitchen design for us. We plan to go and see the last kitchen BG designed next week, once the painters have finished. BG also wants to show us her bathroom as being something similar to what we’d like.
Weather:6°C—16°C; no rain [83.4] 06:30
Posted in General
Comments Off on Bridget Leaves For Wellington.
Bridget, Natalie, and Alex in Sunny Hawkes Bay
SwimGym and then breakfast with Bridget and the girls at Bay Expresso. Later Karola took the girls to “Train World” on Marine Parade in Napier while Bridget and I discussed cottage fittings. We all went to lunch at the Fishing Club in Napier before going to “Kung Fu Panda II” in Havelock North. It’s rather scarier and louder in the cinema than on a DVD at home. After Karola’s fish dinner Bridget and I spent the evening beginning a 3D SketchUp model of the cottage so that we can mark up lighting, power, cabinetry, electrics etc. , starting from the 2D plans imported from the architects computer plans.
We seem to be down to one bantam hen and one rooster after recent depredations of hungry hawkes – at least I think it’s a hawk snacking on the bantams.
The Cottage Refurbishment
Nothing new to report today.
Weather:6°C—15°C; 1.9 mm rain [83.1] 06:00
Posted in General
Comments Off on Bridget, Natalie, and Alex in Sunny Hawkes Bay
Joinery Discussions
Bridget, hearing that the weather was pretty nice up here, came up today arriving mid afternoon.
The Cottage Refurbishment
Les came round and we had a chat with him and Paul. We agreed to a couple of steel beams lengthwise above the living room to replace the support role played by the chimney stack and strengthen the floor above which is currently rather springy. We also talked about joiners and joinery.
Later Les suggested that Paul would be delighted to do the refurbishment of the existing windows and we agree it’d suit us very well so we’ll ask him tomorrow. So that leaves us with joinery tasks of: the 13 new windows (4 modelled on the old existing ones and 9 casement for the kitchen, laundry/loo, and garage); the cabinetry in the kitchen, private bathroom, and laundry; and the stairs and kitchen wooden bench top that juts out between the kitchen and dining room.
Weather:0°C—13°C; no rain [83.5] 06:30
Posted in General
Comments Off on Joinery Discussions
Tallysman Tallies
SwimGym – cold and dark and light rain. Later we went into Hastings for usual monthly blood test and light shopping.
Meticulous Maids (Edith and helper) came this afternoon and did a rapid and effective clean – although with the amount of mud being tromped in it’s only a very temporary improvement.
I walked round the ewes and then the lambs in the orchard. Numbers seem right and all seem pretty active and alert.
The Cottage Refurbishment
Paul and Matthew were here around 7:30 am despite the cold and wet. They began inside the cottage on repairs to the hole left by removing the chimney.
I gave Paul a more up-to-date copy of the design plans and checked – luckily none of the changes I’d neglected to give him earlier had caused any harm; the extended eaves are added on after the main roof supports are complete.
Weather:0°C—8°C; 0.3 mm rain [84.0] 06:00
Posted in General
Comments Off on Tallysman Tallies
Cold Snap Imminent
I stayed in out of the cold- it got colder as the day progressed. I completed my switch to the new Apple operating system version called Lion.
Karola tended her sheep and trimmed the lower branches of the Casurina hedge.
The Cottage Refurbishment
I did a couple of hours in the cottage, taking out light and power fittings and the electric cables.
Karola and I went through the latest design drawings noting things that were not yet quite right or needed more work before we could decide finally.
Weather:3°C—12°C; 4.1 mm rain [84.0] 06:30
Posted in General
Comments Off on Cold Snap Imminent
Wet and cold. Karola spent most of the day at meeting and lunch and dinner with her Federation Of Graduate Women group. I installed the latest version of the Apple Mac operating system called Lion.
The Cottage Refurbishment
Apart from deepening the drains to try and get the surface water away from the cottage, nothing much to report today. I printed off three complete sets of the design drawings – seems that for the 10th July set I didn’t include all the latest ones but I don’t think there’s any critical changes missed.
Weather:9°C—15°C; 0.6 mm rain [83.7] 06:30
Posted in General
Comments Off on
Friday In Winter
SwimGym and then rested in the warm for the remainder of the day as the rain came down.
The Cottage Refurbishment
No work on the cottage today – by Paul and Matthew or by us.
Weather:10°C—12°C; 34.4 mm rain [83.7] 06:00
Posted in General
Comments Off on Friday In Winter
Kitchen Appliance Research
Cold, overcast day with rain setting in late afternoon. Karola went to the dentist to have her new tooth fitted.
The Cottage Refurbishment
Spent a lot of time reviewing kitchen appliance specifications and working on the layout – basically still the one Bridget suggested a while ago.
Weather:4°C—12°C; 14.4 mm rain [83.7] 06:30
Posted in General
Comments Off on Kitchen Appliance Research
Garage Roof Trusses In Place
SwimGym.
The Cottage Refurbishment
Bridget Geenty, kitchen designer, came at 10:00 am for a couple of hours and we discussed our current plans for the cottage kitchen and how she works with her clients. Bridget is an independent designer, working part time and she’s been doing kitchen design for 14 years. She charges $50/hour on top of the cost of the joinery etc. We plan to visit her last job which is in Hastings. She is on the shortlist.
Later, after lunch at Pernel Fruit World, we went to Classic Kitchens in Onekawa. Larry McKenna was very helpful and we discussed out current plan at length. He pointed out that Microwave ovens only open right-to-left so we need to find another spot for it. We also came to the conclusion that a stainless steel bench the length of the kitchen, with a raised lip to trap spills, with two sinks (welded on from below – very secure), a set of four hobs let into the bench top with an under-bench oven below makes good sense for us. He suggested that rather than “Magic Corner II” the similar technology called Le Mans (Lemans) is more space efficient and substantial.
Came home late afternoon to find the roof trusses for the garage up.
Weather:0°C—12°C; 0.1 mm rain [83.7] 06:00
Posted in General
Comments Off on Garage Roof Trusses In Place
Sent e-mail to Midas with photo of exploded muffler and their bill, asking for a refund. Will not hold my breath.
Karola planted more of her under-oaks area with Karamus. The 70+ she’s already planted are all doing well.
The Cottage Refurbishment
Ross from Best-Forsyth came round and said that they would like to quote for the job and there were plenty of solutions short of having a new full electric main back to the roadside for the cottage. Good news. I cancelled the planned job by Tony Lucy, electrician for tomorrow.
Rang Paul of TheEnglishCraftsman and gently chivvied him along to give us quotes soon. He said by end of week.
Sent e-mail to Margaret Barker seeking name of the guy on the IDS trip to Queenstown in order to find out the agent who imports Jotul woodburners – so we can order the small classic Jotul 602.
Jotul 602:
- Smallest Cast Iron woodstove on the market with detailed lattice door and decorative side panel motif
- Incorperates Jøtul’s non-catalytic clean burn technology
- One easy air control lever operates the entire stove
- Alcove approved for both the US and Canada
- Standard bottom heat shield
- Rear or top exit flue collar with adaptor
- Fully functional cookplate
I dug a bit more out at the end of the open stormwater drain from the cottage to the ha-ha, clearing the entrance to the plastic pipe underground and through the retaining wall. It still doesn’t flow freely so that part of the proper stormwater drain may need doing too, I don’t think we can rely on the plastic pipe. It’s only an additional 10 metres so not a problem.
Weather:-3°C—12°C; 0.1 mm rain [83.2] 06:30
Posted in General
Comments Off on
Kitchens – Choices
SwimGym. Very cold. Later, warm in the sun. Lunch (delicious) at Taste Cornucopia in Hastings.
Five sheep from over the road had got out and were milling round our back door when we got home, eating anything that looked remotely like a flower or shrub. Most of them were lame. Shooed them back out onto the Avenue and they ran back home through the open gate as if they knew very well where home was. Saw Jim Cornes (I think) coming over with a sheep dog to take them back to their paddock.
The Cottage Refurbishment
Spent most of the day on kitchens, “the stove shop”, “kitchen Studio”, and Harvey Norman.
The expansion grooves have been cut in the garage concrete slab. I did ask why there were no bolts sticking up all round the edge, to fasten the walls to. Apparently these days they use expansion bolts – drill a hole through the wooden bottom plates into the concrete and then the bolt is dropped in and turned and it locks itself into the hole. Faster than trying to drill holes in the bottom plate to match the bolt sticking up out of the concrete.
Bridget helped with some design ideas for laying out the kitchen and sent us a Sketchup sketch by e-mail.
Weather:-2°C—13°C; 0.1 mm rain [83.4] 06:30
Posted in General
Comments Off on Kitchens – Choices
Dismantling Work
Scrounged a bit of the sand and gravel left over from making the cottage garage slab and used it to make a smoother path from the back door of the homestead out to the drive.
The Cottage Refurbishment
We spent the afternoon, until dark, working on the cottage. I removed light and power fittings downstairs and the pipework in the bathroom and some left over in the old kitchen. We also removed the bathroom basin and cistern and detached the bath from its pipes although it’s too heavy for us to take out of the cottage ourselves. Karola did a lot of cleaning, removing the layers of mud accumulated over the past two weeks. We carted off the old sink that Paul and Matt had already dismantled.
Weather:-2°C—14°C; no rain [83.2] 06:30
Posted in General
Comments Off on Dismantling Work
Jenny and Noel’s For Dinner
Very cold morning. Didn’t really get going till after lunch apart from some inconclusive discussion about kitchens. Karola moved her ewes from the Orchard paddock to next door for the day and then had a chat with Alan the orchardist. He’s planted 8 replacement peach trees, where the original tree had dies of disease. Three of these died season before last but Alan was unable to get any replacements of the correct Tutara Star variety, and a further five needed replacing this season. Apparently our lambs, being curious creatures, had started nibbling the green cylindrical shields placed round the new trees and Alan worried that they might take to nibbling the trees themselves next so Karola offered to move the electric fence so that the lambs were restricted to the back of the orchard, beyond where the peaches are. It took her the rest of the afternoon.
Matt Saunders from The Stables across the road dropped by to see if we had anything to report about the car seen leaving our place at speed early evening yesterday – he’d rung about the close encounter with a speeding car last night. We think it was the hoodied young man who’d been here all day tending the new concrete. Matt and I discussed the electricity mains challenges we have and he thinks we do have three-phase mains up to the garage fuse bos so might be able to exploit that to avoid getting another cable laid back to the road.
Meanwhile I dismantled the old electricity box and some adjacent wiring on the side of the cottage and, using the Fergie, filled in a couple of holes near the cottage not now needed for extra posts for the “walkway” and also put a lot of earth on top of one of the sheep graves which had been excavated by rats.
Later we went to Jenny and Noel’s for dinner, Karola took a beef casserole, Jenny supplied the veg and fruit salad pudding.
The Cottage Refurbishment
A little dismantling work and filling in a couple of holes, as per above.
Weather:2°C—13°C; no rain [83.3] 06:30
Posted in General
Comments Off on Jenny and Noel’s For Dinner
Concrete Slab For Cottage Garage Laid
SwimGym. Hearty breakfast. Rest of morning spent moving logs; the area near the 133 entrance is now clear for Karola to plant trees among the oaks. Karola gathered several trailer loads of mulchable branches.
The Cottage Refurbishment
To our astonishment, it was just beginning to become light enough to see, we met a concrete truck coming in as we went out to SwimGym at 6:55 am. When we came back the concrete slab for the cottage garage had been poured. One man stayed all day. As he said, his job was to stop eg the geese from mucking up the smooth concrete surface and to apply several smoothing runs as the concrete was in the process of setting.
Karola has agreed to there being a thin flat strip along the high point of the ceiling in the laundry, kitchen, dining room and bathroom – no more than 14″ wide and made of the same materials as the rest of the roof in that area. This makes tying in the new and old pieces of the building much easier and makes the apex of the ceiling two less severe joints rather than one very sharp one, which is hard to finish neatly.
Weather:-3°C—10°C; no rain [82.6] 06:30
Posted in General
Comments Off on Concrete Slab For Cottage Garage Laid
Framed! Well Almost.
Cold, horrid winter’s day. Another hour removing branches from the area near the 133 gate down to the holding area near the 121 gate.
The Cottage Refurbishment
The cottage framing delivered earlier this week is taking shape. The framing for the laundry, kitchen, and passage is up and the underfloor of the laundry and passage is laid. Reinforcing steel mesh over plastic waterproof membrane on sand on compacted hardfill for the garage slab is complete. Council inspectors have approved the subfloor framing for the new extension piece of the cottage and the garage slab preparation.
Weather:0°C—15°C; 0.2 mm rain [82.7] 06:30
Posted in General
Comments Off on Framed! Well Almost.
WX2288 Is Back Home
SwimGym. Haircut at 9:30am.
I rang Heath Goldfinch at his garage in Taradale and he’d just been going ot ring me – the Landrover is fixed and not too expensive. We went round late afternoon and picked it up. He’s done a very good job – had to replace two mufflers – the front one which had exploded twice, and the back one which was very blocked. Heath said the Wellington Midas people had not only put on an undersized muffler but hadn’t checked the back muffler and hence the 2nd explosion. Heath got a pair of 2nd hand mufflers from Landy Heaven (who recommended Heath to us in 1st place) and to my delight and amazement the bill was #350.
I did another hour of log moving with the Fergie.
The Cottage Refurbishment
Thanks to Karola spotting it today we were able to stop the use of two support posts 2/3rds of the way across the walkway. It means using slightly more expensive laminated beams but otherwise apart from a little lost time by the builders (the holes for the posts and painting them with primer) no harm done. This way we can, if we wish, back a car in under the walkway and decant someone or something onto the kitchen verandah and into the house in the dry – sometimes much easier than trying to do the same thing when the car is in the garage.
Tony Lucy the electrician has not called back – he said he’d call last Monday, “black mark” for Tony. I called him. He says he’ll come and do the mains tidy-up and the reconnection of the pump-shed power via the kitchen fuse box next Wednesday. He also says that there’s no way we can extend our current electrical mains from the homestead garage out to the cottage. “Wrong Answer”. We’ll get several second opinions on that until hopefully we get a better answer. Karola got onto Best-Forsythe who did the homestead rewiring competently if expensively some years ago.
Weather:6°C—18°C; 0.6 mm rain [83.2] 06:30
Posted in General
Comments Off on WX2288 Is Back Home
Diesel – Is It Evil
No news of the Landrover which is a bit ominous.
Late afternoon I spent an hour with the tractor moving fallen and cut-up logs near from near the 133 entrance; Karola intends to plant a few more trees there this winter.
The Cottage Refurbishment
No news from the electrician, Tony Lucy.
Steve Broughham from F L Bone came mid morning to discuss heating – room and water heating for the cottage. We are pretty set on having a heat pump but listened anyway to his advice re using a diesel fired boiler. He’s getting us a bit more info from their main supplier Grant’s in Ireland.
Bridget and Chris advise against Diesel: inflammable near the buildings, has to be topped up regularly as diesel “goes off” after 2-3 months – never mind that it’s unsustainable “fossil fuel”.
I printed out a full set of the latest design drawings for us and for Paul – with the right walls labelled North-South-East-West.
Another cubic metre, this time of sand, for the cottage garage floor. Paul and Matt have compacted the hard fill and topped it with sand and laid out the reinforcing steel so its ready for council inspection and then the concrete. Things are going apace.
Weather:8°C—16°C; 0.3 mm rain [83.3] 06:30
Posted in General
Comments Off on Diesel – Is It Evil
Prefab Wood For Cottage Arrives
SwimGym.
The Cottage Refurbishment
Paul Winstanley and his wife Katie(The English Craftsman Ltd 021-103-6683 & 0800-494-6369, paul@theenglishcraftsman.co.nz) arrived from Masterton around 11:30 am and we spent the next hour or so discussing the cottage windows, doors, and floors. I suspect he will be very expensive ($575 just to come up here for two hours and they were obviously having a little holiday at the same time). Based on his advice:
- we will not be getting any of the old Kauri doors stripped because it’s apparently impossible to get old tongue & groove completely clean of paint without actually taking it apart plank by plank
- we will not be reusing the old kitchen window because it is just too rotten, especially at the wood joints
- that leaves 6 double-hung sash windows to be refurbished, 4 brand new double hung sash windows, and 9 new smaller casement top-hung windows – this includes the upstairs and the garage.
- the floors in the living, dining, bedroom and upstairs could be given the special clean-and-wax treatment to retain the age patina – it does look good – and it costs about $45 a square metre – roughly the same as sanding and polyurethaning – allegedly
At Paul the Builder’s request I got John Pollock at Elms to bring us ten or so cubic metres of gravel – and some more sand tomorrow. The base of the garage is now built up ready for compacting and then covering with a plastic waterproof membrane and then the reinforcing steel and then it’ll be ready to pour the floor slab. Some of the gravel was used to build up the drive near the cottage; it’s become very muddy.
After lunch a Carters truck arrived and decanted all the prefabricated walls and roof trusses – one does so hope they got the measurements right.
Weather:7°C—19°C; no rain [82.7] 06:30
Posted in General
Comments Off on Prefab Wood For Cottage Arrives
GST for Another Two Months Done
Fierce gales and some rain early in the day but sun prevailed and the wind calmed. An “inside” day. Karola’s GST done (10 days late).
The Cottage Refurbishment
Nothing to report today.
Weather:4°C—15°C; 3.2 mm rain [83.0] 06:30
Posted in General
Comments Off on GST for Another Two Months Done
Winter Sheep May Safely Graze
Slow day. Went round the two lots of sheep and they seemed all to be OK. Plenty of grass. Karola also went and inspected her pregnant ewes and gave them some sheep nuts. Karola also went shopping briefly in Hastings.
I dumped a the remained of the rubble from the old fireplace onto the track Karola is developing from the Homestead back door to the drive, across where the cottage used to sit.
The Cottage Refurbishment
Nothing to report today.
Weather:8°C—16°C; 1.3mm rain [83.3] 06:30
Posted in General
Comments Off on Winter Sheep May Safely Graze
Cottage Briefing Paper Updated
SwimGym – a bit milder today but not really very nice outside.
The Cottage Refurbishment
Front varandah sub-floor timbers now in place. Several of the kitchen verandah posts are up too.
Karola and I amended our June 2010 “brief” re the cottage “refurbishment” and gave Paul and Matt copies to read.
I sent Brett an e-mail including the observation that he’d got the north/south directions on the drawings wrong so that his drawings said North where we said East etc and I hoped no-one would be confused by that. Hmmm. Be a pity if trenches were dug in the wrong place or wires put in the wrong walls because of that – very Hubble Hubble.
Weather:5°C—14°C; no rain [82.9] 06:30
Posted in General
Comments Off on Cottage Briefing Paper Updated
Cottage Continues
Karola went shopping and did some outside work; I stayed inside all day – sunny in patches but cold.
The Cottage Refurbishment
The wood man came this morning and Paul worked with him on the measurements of all the walls, including the garage walls and window and door surrounds.
I chatted to Paul about the (re)use of wood for floors and ceilings. The old bathroom floor is to be reused to fill where the old fireplaces and chimney were. The Matai flooring saved from the rickety old extension is to be reused to make the floor of the new kitchen bare native wood T&G to be same size and almost same look as the Kauri T&G on the dining room floor. The floor of the dining and kitchen areas are bare wood and so need to look very similar; the ceilings of these two areas will be painted so we have more flexibility. The dining room’s existing T&G ceiling (which is probably Rimu rather than Kauri) will remain. We’ll get some pine sawn to match to do the kitchen with the same width, thickness of T&G.
Les came round late afternoon and explained the latest, and final, window/door framing arrangements – which we’d seen on his revised plans yesterday and are in agreement with.
Paul and Matt added some piles for the front verandah so that, instead of using the cottage as the support for one side of the verandah it is completely free standing. This is recommended, and I think desirable – and I’m not sure why the plans didn’t allow for those extra piles. This way water coming down the wall drips straight onto the ground and isn’t blocked by the edge of the verandah. We’re not intending to heat the sun porch other than by direct sunlight so the draught won’t be a problem.
Weather:8°C—18°C; 1.2 mm rain [83.3] 06:30
Posted in General
Comments Off on Cottage Continues
Sub-Floor Framing Complete
SwimGym then inside programming with Bridget in the morning; some tractor work in the afternoon.
The Cottage Refurbishment
Exciting to see the timber sub-floor of the new cottage extension in place today. Very solid looking. As the timber firm are visiting Paul tomorrow to measure up for the framing for walls etc we have to decide finally on the size and placement of the windows today. We picked up final design drawings this afternoon and checked that, as far as we can tell, the windows and doors and walls are all in the right places.
Karola and I are smoothing over and filling in a bit of a path from the back door of the homestead across to the drive.
Weather:9°C—16°C; no rain [83.4] 06:30
Posted in General
Comments Off on Sub-Floor Framing Complete
Finalised the Window Sizes and Positions
Wet, miserable day but had some good time working on programs with Bridget. Karola went to town late afternoon after retrieving her sheep from their day-time pasture next door. They were keen to come home in the wet and mud, more interested in some sheep nuts from Karola than foraging in wet, long grass.
The Cottage Refurbishment
Went to see Les in the afternoon, discussing final choices for the position and size of windows. Les came back to Karamu and we finalised the east-facing wall decisions on the spot. Karola observed that some of the windows were too wide being three panes wide, with panes matching the big sash windows downstairs. By reducing that to two wide and having three of them across the kitchen sink-bench we think it’s a big improvement.
Given that the ground is sodden and big puddles everywhere it was absolutely the best idea to get the piles concreted in last night, before the rain came.
Today Paul and Matt began on the inside of the existing cottage, removing cupboards and walls where not needed.
Weather:5°C—12°C; 17.6 mm rain [83.7] 06:30
Posted in General
Comments Off on Finalised the Window Sizes and Positions
Rest Of Cottage Piles Concreted In
SwimGym – and it was a heavy frost this morning, followed by a mainly sunny, bright day.
I spent a couple of hours chainsawing the large fallen English Beech limb – got all but the main limb done but it’s too thick (500-600mm) and too precarious for me to tackle so we’ll leave that for Tricky Trees.
Karola is preparing a pathway through the old cottage site so we can get from our temporary new back door steps to the driveway and on to the garage in relative safety.
We took the Landrover to Taradale this evening for fixing tomorrow.
The Cottage Refurbishment
Paul and Matt made final preparations for the concrete for the piles for the cottage extension and the new verandahs; the concrete truck arrived late at around 4:00 pm and Paul and Matt finished this concreting in around 6:00 pm – in the dark lit by Karola’s car headlights.
Les sent an e-mail of the authorised plans for the foundations, authorised so, despite Carl the moving man disputing it, it seems there were enough piles on the plan. Paul still thinks Les/Brett and the council are wrong in that the extra piles Carl added are needed. So now, moving on ….
Weather:-1°C—11°C; 8.0 mm rain [83.4] 06:30
Posted in General
Comments Off on Rest Of Cottage Piles Concreted In
Bright, Sunny and Cold
The Cottage Refurbishment
All the old concrete piles removed.
Weather:-2°C—12°C; no rain [83.2] 06:30
Posted in General
Comments Off on Bright, Sunny and Cold
Gill & Ben Return Safely
Cold day. Gill TXTd progress back, from Heathrow airport, HongKong airport, then Auckland airport – it was good to hear the progress despite threats of strikes (UK) and ash (NZ).
The Cottage Refurbishment
Both in thrall to nasty colds but we made a start on removing the old piles from the previous cottage site and taking them on the tractor down to the fencing dump near the 121 entrance.
Weather:0°C—11°C; no rain [82.7] 06:30
Posted in General
Comments Off on Gill & Ben Return Safely
Not Enough Ergs, Possibly
The Cottage Refurbishment
workforce all turned up; sunny day but cold and still very muddy. Cottage lowered onto piles and fastened down except in a couple of places where we hope the joists etc will straighten out and sit flat on the piles in a few days time. Paul and Matt continue with the garage foundations and readying their piles (for the extension and front verandah) for concreting on Monday.
Paul suggested we talk to electrician Colin Lucy, youngish chap, who came round this afternoon and we’ve engaged him to do a small initial job before we decide whether to employ him for the wiring of the cottage. The small job is, now the cottage is moved and the cottage power is no longer needed, to connect the mains electricity from the garage mains/meter board directly to the fuse-board in the kitchen of the homestead, bypassing the old, very damp, and probably dangerous old junction box on the end of the verandah next to the water pump. This will leave the cable out to the pump shed in limbo so at the same time we’ve asked Colin to connect that cable to a new fuse in the kitchen fusebox. We also discussed the radio interference I get and so a new earth rod will be attached and that may help. Somewhat worrying is that the length of mains electricity cable may exceed regulations – from road to homestead garage to: cottage, homestead, pump shed is several hundred yards. Solutions may be expensive. Colin will let us know next week based on distances he measured today.
Weather:7°C—13°C; 0.1 mm rain [83.2] 06:30
Posted in General
Comments Off on Not Enough Ergs, Possibly